Highways England, as part of a Regional Investment Strategy, is resurfacing the northbound carriageway and the slip roads of the M6 between Lancaster and Carnforth.
They will be writing to all residents who live on one of the proposed diversion routes to forewarn them of the closure of the M6 as this will generate more traffic along the route.
The construction will start on Friday 13 September 2019 and will require full overnight closures of the M6 northbound between junction 34 and junction 35. The table below sets out the programme over the four weekends:
Weekend 1 13 – 15 September | Fri | Sat | Sun |
Northbound Junction 35 exit & entry slip roads closed for resurfacing | 8pm – 6am | 8pm – 6am | 8pm – 6am |
Weekend 2 20 – 22 September | Fri | Sat | Sun |
M6 Full closure northbound carriageway from junction 34 | 9pm – 5am | 9pm – 5am | 9pm – 5am |
Weekend 3 27 – 29 September | Fri | Sat | Sun |
M6 Full closure northbound carriageway from junction 34 | 9pm – 5am | 9pm – 5am | 9pm – 5am |
Weekend 4 4 – 6 October | |||
M6 Full closure northbound carriageway from junction 34 | 9pm – 5am | 9pm – 5am | 9pm – 5am |
Whilst the road is closed they will undertake cyclic maintenance including gully cleaning, drainage inspections, linear drainage clearance, road sweeping & structures maintenance.
If you require any further information regarding the planned works please e-mail: M6Jct34P1@highwaysengland.co.uk.